Santa Barbara Race ClubDue-Diligence Portal · Advisory by IAG

Orientation

Executive Overview Project Vision Project Background

Analysis

Construction Cost Revenue & Employment Visitor Spending Market Research Comparable Facilities Economic Impact

Plan

Business Plan Financial Model Overview Capital Structure Construction Budget Membership Strategy Residential Development

Execution

Risk Analysis Development Phasing Project Timeline & Roadmap Governance & Management

Action

FAQ Download Center Contact & Investor Info
Proposals / Motorsports / Santa Barbara Race Club / Execution / Project Timeline & Roadmap
Execution

Project Timeline and Roadmap

A conventional ~24–32 month private-development build across nine phases, with staffing mobilized as facilities complete and the operating ramp running from first sales to saturation.

~24–32 mo
Phase I build duration
9 phases
Construction sequence
Timeline
2027 → 2033
First sales → opening
~2036
Saturation
Construction phasesRoadmap & scheduleStaffing & ramp

Construction phases (indicative)

A conventional private-development methodology — not an accelerated three-shift build. Several phases overlap, so durations are phase lengths compressed within the envelope through concurrency.

Phase I construction sequence (~24–32 months).
PhaseDurationScope summary
1Pre-construction / planning3–4 moDesign, permits, notice to proceed, funding
2Site preparation and excavation8–12 moClearing; mass excavation (flat-site); access road
3Track construction and safety features6 moCourse civil, surfacing, barriers, marshaling
4Foundation and structural6 moPads, underground utilities, foundations, structure
5Building construction and finishing8–10 moCore buildings; MEP trim-out; finishes
6Infrastructure and roadwork6–8 moParking, roads, network, off-road course
7Bridges / structuresup to 6 moConcurrent from the foundation phase
8Vertical transport3 moElevators and stairs
9Commissioning and final inspection3–4 moStart-up, commissioning, inspections

Visualize the schedule

Interactive project roadmap

Select a milestone to view its detail. The roadmap runs from first sales through to membership maturity.

2027 — First salesFirst real-estate and membership sales commence ahead of construction.

Construction schedule

The nine construction phases across the build. Adjust concurrency to compress the schedule within the envelope; several phases overlap, and bars show indicative start and duration in months.

40%
~29 monthsTotal build duration
ModerateOverlap intensity

Conventional private-development methodology; durations compress within the ~24-32 month envelope through concurrency.

Staffing and the operating ramp

Construction employment is a one-time impact. Staffing follows the Project Mobilization Model — departments activate as their facilities complete, then expand after opening with demand.

2027
First sales
2033
Opening
2036
Saturation

Engine activation: OEM → Hotel → Hospitality → Residential → Business Park → Membership → Recurring visitor spend. Peak on-site construction workforce ~640.

The residential vertical build is a separate, absorption-paced program that interfaces with site preparation and infrastructure but is not part of this construction sequence or the budget.

Related analysis

Development PhasingConstruction Budget
PreviousDevelopment PhasingNextGovernance & Management
Confidential. Prepared by Ignition Advisory Group for SBRN Management LLC. Access-controlled; not for public distribution. Supporting documentation is available through the References & Sources section.